From the Challenger Report: If a change occurs late enough, it will have an impact on the serial processes. 1/
-
-
Replying to @wycats
"In these cases, additional resources will not alleviate the problem," 2/
1 reply 1 retweet 2 likes -
Replying to @wycats
"and the effect of the change is absorbed by all downstream processes, and ultimately by the last element in the chain" 3/
1 reply 1 retweet 3 likes -
Replying to @wycats
"Once a particular process has started, if a substantial change is made to the flight," 4/
1 reply 1 retweet 1 like -
Replying to @wycats
"but the process that preceded it and supplied its data may also need to be repeated. If one group fails to meet its due date," 5/
1 reply 1 retweet 1 like -
Replying to @wycats
"the group that is next in the chain will start late. The delay then cascades through the system." 6/
1 reply 1 retweet 1 like -
Replying to @wycats
TLDR: it's easy to claim that up-front "certified" design is "the right way" to do engineering, but that has never ever been true. 7/7
1 reply 4 retweets 10 likes -
Replying to @wycats
List of customer changes from the reportpic.twitter.com/EXtMaZSV0G