If a proj milestone requires 3 tasks to be complete, and ea task has a 50% chance of being late, what is the probab. milestone will be late?
-
-
-
Replying to @vgr
yeah, I guess that was easy. Still surprising though intuitively
1 reply 0 retweets 1 like
Replying to @fortelabs
it's actually classic stats 101 type homework problem on coin tosses
7:52 PM - 22 Sep 2016
0 replies
0 retweets
1 like