Tiago Forte@fortelabs·Sep 23, 2016If a proj milestone requires 3 tasks to be complete, and ea task has a 50% chance of being late, what is the probab. milestone will be late?12
Tiago Forte@fortelabs·Sep 23, 2016Replying to @vgryeah, I guess that was easy. Still surprising though intuitively11
Venkatesh Rao@vgrReplying to @fortelabsit's actually classic stats 101 type homework problem on coin tosses2:52 AM · Sep 23, 20161 Like