If a proj milestone requires 3 tasks to be complete, and ea task has a 50% chance of being late, what is the probab. milestone will be late?
Conversation
Replying to
yeah, I guess that was easy. Still surprising though intuitively
1
1
Replying to
it's actually classic stats 101 type homework problem on coin tosses
1