I'm glad @fulhack wrote this clear analysis about estimating software projects. It maybe needs another explanation about why the mean and median completion time for software development tasks are so different, so here's my take. (1/4)https://twitter.com/fulhack/status/1117968632536010754 …
-
-
I'm more familiar with the design phase of major works rather than construction phase. Estimating individual tasks now in software feels similarly fuzzy, although to be fair, sometimes a co. would pay/spend $$$ to go from +/- 70% costs to a +/- 25% estimate
-
My guess on only seeing 1-5x in construction, compared to higher # in software, is related to more $/time upfront to spec out a project (this phase can be years in an of itself, for say a $40B LNG plan), which is not possible in software (different velocities to market).