I was talking to someone about bikeshedding earlier today and the general category of fully general participation, and it struck me that there are some fully general questions which are probably useful to have someone ask. Some examples:
-
Show this thread
-
Do we have a clear success metric? What would cause us to kill this project early? Who is the DRI for this? (“directly responsible individual”) Is this project the optimal use of the DRI’s time? Does this project gain anything by being done now? Who owns this going forward?
4 replies 9 retweets 128 likesShow this thread -
Replying to @patio11
Hi, woukd you explain what’s the difference between DRI and “Who owns this going forward”? Is that not the same person? Thanks.
1 reply 0 retweets 1 like
Sure. DRI gets the project “done”, but many projects will be maintained for an arbitrary amount of time, and that generally implies they are owned by an organization / team not a person. Important to specify who, exactly.
Loading seems to be taking a while.
Twitter may be over capacity or experiencing a momentary hiccup. Try again or visit Twitter Status for more information.