With dependencies you have two deadlines - minimum, when the dependent task can kick off and then e3/alpha/beta/rc (and most likely two separate "engagement" estimates)
Oh you absolutely need *dependencies* - certain things cannot start right away. But in code task are rarely "done" done. You almost always come back to iterate more, fix, add extra functionality, optimize.https://twitter.com/ChristerEricson/status/1027979769868996608 …
-
-
Deze collectie tonenBedankt, Twitter gebruikt dit om je tijdlijn te verbeteren. Ongedaan makenOngedaan maken
-
-
-
Sure, but that's irrelevant w.r.t. scoping, i.e. what I've been talking about.
Bedankt, Twitter gebruikt dit om je tijdlijn te verbeteren. Ongedaan makenOngedaan maken
-
-
-
hold on, actually you can do a lot of scoping without dependencies! Answering the question “is this out of scope?” can be done without dependencies. Answering the question “can it be done before deadline” needs dependencies. The former is the important question.
Bedankt, Twitter gebruikt dit om je tijdlijn te verbeteren. Ongedaan makenOngedaan maken
-
Het laden lijkt wat langer te duren.
Twitter is mogelijk overbelast of ondervindt een tijdelijke onderbreking. Probeer het opnieuw of bekijk de Twitter-status voor meer informatie.