. board currently hearing from staff about problems with concrete plinths and other "quality issues" with construction (missing rebar, poorly consolidated concrete + repair mortar that didn't work to fix it) that will delay the completion of East Link light rail
7
79
Crews found cracking (previously reported) in the blocks used to attach the rails; ST is also replacing all of the inserts used to attach the rails to these blocks because they've been stripped.
2
22
In Federal Way, where the rail line will run along I-5, an effort to stabilize the ground failed and a mudslide pushed a 200-foot embankment nine feet. ST is looking for a fix but "until we determine a solution, we won't be able to identify a new timeframe for this project."
4