A U.S. judge canceled a key permit for the Keystone XL oil pipeline that’s expected to stretch from Canada to Nebraska, another setback for the disputed project that got underway less than two weeks ago following years of delays.https://apnews.com/89e3f21d344db86b8743665ea66b892c …
-
Show this thread
The Army Corps of Engineers failed to adequately consider effects on endangered species in rivers the pipeline would cross. The ruling, however, does not shut down work that has begun at the U.S.-Canada border crossing in Montana, according to attorneys in the case.