About $100 each. So the project was * $600 cement pad * $100 rebar * $1,000 cement blocks = ~$2k https://twitter.com/BrowningMachine/status/908743876940242945 …
and it was sort of mashed up with the drainage project, which * $500 drainage materials * $1,500 excavator + fill * ~$500 labor = $2,500
-
-
so it's been about $4,500 in the last month or so on that section of the yard. Which blows. OTOH, it's now 100% done and will last decades.