Posted 'WCC Library Learning Commons Service Desk Virtual Tour' to blip.tv:
7:27 PM Oct 30th
from blip.tv
-
We plan to use dry-erase wall paint in the study rooms & classroom in the new building! How cool is that?
6:18 PM Aug 28th
from Power Twitter
-
We have received the pre-final plans for the new building! Now for the careful review.
11:22 AM Jun 15th
from Tweetie
-
Projected Project Timeline: Complete Design 09/09; Bid 10/09; Award Contract & Notice to Proceed 01/10; Construction 02/10; Completion 07/11
1:09 PM Mar 18th
from Power Twitter
-
Presentation: "Green Library - Silver Standard" by Architects Hawaii's LEED specialist Glen Yokotake, today at 11am in WCC's Hale Kuhina 115
12:52 PM Mar 12th
from Tweetie
in reply to wcclibrary
-
Meeting with the architechs about the data, power & furniture plans.
12:23 PM Feb 18th
from Tweetie
-
As a "green" building, the LLC will have solar panels.
4:16 PM Jan 16th
from web
-
See an animated virtual fly-thru of WCC's planned Library Learning Commons building
4:14 PM Jan 16th
from web
-
The power has come back on, and the Library has network access again.
3:29 PM Dec 12th, 2008
from twhirl
-
Our plans for the new building include a classroom for information literacy instruction - with computers!
5:50 PM Jul 18th, 2008
from web
-
The LLC will have a media lab, group study rooms, the Tutoring Center, and more! The latest draft floor plans at
5:58 PM Jun 17th, 2008
from web
-
The architects' conceptual floor plans reveal a three-story atrium to maximize natural light The view should be great, too!
6:20 PM Apr 15th, 2008
from web
-
People filling out our Library Survey at have lots of great suggestions about the new building.
7:40 PM Apr 4th, 2008
from web
-
Trying to figure out which areas of the new building will need air conditioning and which can have natural ventilation. Hmmm. Any ideas?
3:04 PM Mar 17th, 2008
from web
-
See "Commons 2.0" by Bryan Sinclair at to get an idea of what we envision for the new building.
5:48 PM Mar 13th, 2008
from web
-
Proposed Timeline: Planning & design through spring 2009; Construction summer 2009 through end of 2010; completion in early spring of 2011.
5:39 PM Mar 13th, 2008
from web
-
We met with Architects Hawaii, who use an "integrated design" approach to planning- apropos for an integrated services & resources building!
5:23 PM Mar 13th, 2008
from web
-
We put Conceptual floor plans on display in the Library, along with envelopes to take your suggestions on furniture, layout, design, & more.
9:44 PM Mar 10th, 2008
from web
-
Last week, we got word that we could proceed with planning for the new building.
3:36 AM Mar 7th, 2008
from web
|
- Name WCCLLC
- Location Kaneohe, HI, USA
- Web http://wccllc.blo...
- Bio Windward Community College designing & building a new Library and Learning Resource Center
|