Get short, timely messages from CumbriaCountyCouncil.

Twitter is a rich source of instantly updated information. It's easy to stay updated on an incredibly wide variety of topics. Join today and follow @bridgewatch.

Get updates via SMS by texting follow bridgewatch to 40404 in the United States
Codes for other countries

Two-way (sending and receiving) short codes:
Country Code For customers of
Australia
  • 0198089488 Telstra
Canada
  • 21212 (any)
United Kingdom
  • 86444 Vodafone, Orange, 3, O2
Indonesia
  • 89887 AXIS, 3, Telkomsel
Ireland
  • 51210 O2
India
  • 53000 Bharti Airtel, Videocon
Jordan
  • 90903 Zain
New Zealand
  • 8987 Vodafone, Telecom NZ
United States
  • 40404 (any)

bridgewatch

  1. Bridge now open after 72 days of construction and 5 weeks ahead of schedule.
  2. Work is continuing on the white marking, verges and signage. Street lighting will be complete early this week.
  3. Bridge will open on Wednesday 21 April
  4. All surfacing will be complete by the end of the week. Posts for rail fencing are being installed on the west carriageway of the new road.
  5. Tarmac is continuing to be laid on the approach roads and footpaths.
  6. Street lighting is in place on both sides of the bridge. The tie-ins to the roundabout on New Bridge Road are also nearly complete.
  7. Paving to the approach footpaths is also underway and the new entry to the football ground is nearing completion.
  8. Finishing works are underway, with tarmac being laid and street lighting installed. Kerbs have been fitted to the new roundabout.
  9. The new entry to the football ground is nearing completion.
  10. Kerbs have been fitted to the new bridge roundabout. Paving to the approach footpaths is underway.
  11. Finishing works are underway with tarmac being laid and the installation of new street lighting.
  12. View photos from each stage of the construction process in our bridgewatch gallery. http://bit.ly/aZ59eQ.
  13. The bridge decking is now complete and the team has started widening the approach road on the Northside of the bridge.
  14. People in north Workington are being informed about new traffic management plans around the new temporary road bridge. http://bit.ly/9NjOqd
  15. A reinforced earth retaining wall is being constructed adjacent to the roundabout on New Bridge Road.
  16. The bridge is now in its final position and tarmac will be laid next week.
  17. Decking work is being laid and will be complete by the end of the week. Resurfacing of the access road to the football club will begin soon.
  18. The new bridge now spans the river - it was lowered into place over the weekend.
  19. The final bridge push will take place over the weekend and will be jacked down to its permanent level. http://bit.ly/9gaUiW
  20. Watch the ITV Border news footage from 4 March. http://bit.ly/bLc0Qw