VWBG-14: Builders love when lumber shows up to the job. Framing starts tomorrow.
1:42 PM May 30th
via Twitter for iPhone
-
1 CO received. 1 Permit app submitted. 1 inspection passed. 1 footing poured. Great way to end the week before the holiday weekend.
2:16 PM May 25th
via Twitter for iPhone
-
@ tweeting during graduation - a different world. Congrats Jared (son of a JK Development)!
10:46 AM May 4th
via Twitter for iPhone
in reply to jaredshafran
-
No matter what the papers say, new construction is still alive. New home starts today on Lot #14 at Vista Woods BG.
5:36 AM May 4th
via Twitter for iPhone
-
The Aspen model furniture being assembled (PIC), thanks to our new partnership with @.
7:21 AM May 2nd
via web
-
Builder's dream: crisp Fri AM on jobsite. Check out the Bayberry model being built at Vista Woods Shawangunk (PIC).
5:07 AM Mar 30th
via Twitter for iPhone
-
It's official! Broke ground on our newest community Vista Woods Shawangunk. Bayberry model on Lot 3.
8:16 AM Mar 7th
via Photos on iOS
-
Cucuzza Residence: guys from Allstate Fabricators installing the granite (PIC).
6:38 AM Jan 18th
via Camera on iOS
-
VWBG#8: ready to start sheathing (PIC)
4:53 AM Jan 10th
via Photos on iOS
-
VWBG#2: Who said construction stops in the winter? Getting ready to install the roofing (PIC)
5:13 AM Jan 4th
via Camera on iOS
-
VWBG#8: Cold but sunny. Great day to make some progress framing the Wasley Residence (PIC)
5:11 AM Jan 4th
via Camera on iOS
-
Thanks much to the guys at Ultimate Plumbing for our Chanukah cake.
11:40 AM Dec 28th, 2011
via Camera on iOS
-
Cucuzza Residence: can anyone guess what Igor from Affordable Floors has done in this photo?
7:03 AM Dec 6th, 2011
via Photos on iOS
-
VWBG: there's that dozer we needed (PIC)
5:05 AM Nov 10th, 2011
via Photos on iOS
-
VWBG: looks like we need a dozer to move some stone. Trying to get road ready to pave before winter. Will we make it?
4:56 AM Nov 10th, 2011
via Camera on iOS
-
Cucuzza Residence: the guys from Acies Group are making great progress on the stucco (PIC). Insulation starts today!!
6:21 AM Nov 3rd, 2011
via Photos on iOS
-
VWBG: Guys from 5L Enterprises prepping for outlet structure/ storm drainage (PIC) at Vista Woods Blooming Grove.
8:51 AM Nov 2nd, 2011
via Photos on iOS
-
LR#6: Stucco began On Friday (PIC). Only a few more days till weathertight. Then we start insulation inside.
6:56 AM Oct 24th, 2011
via Camera on iOS
-
LR#6: Replacement window installed. Ready for housewrap/drainage plane/stucco outside and air sealing/insulation inside.
12:08 PM Oct 18th, 2011
via Twitter for iPhone
-
ELLENRIDGE: Air sealing / Insulation complete & inspected. Time for Minh and the C.P.M. guys to hang our drywall.
4:50 AM Oct 17th, 2011